• Link to X
  • Link to LinkedIn
  • Link to Mail
  • ABOUT UI
    • Business Partners
    • Careers
    • Contact Us
    • News & Press
    • Our Team
    • Press Releases
    • Branding Guidelines
  • CONTACT
Uptime Institute Blog
  • Journal
    • Journal Home
    • Executive
    • Operations
    • Design
  • AI Services
    • AI Infrastructure Advisory
    • AI Custom Support
  • Tier Certification
    • Overview
    • Design
    • Construction
    • Operations
    • Tier Gap Analysis
    • Prefabricated/Modular
    • Tier Certifications List
  • Professional Services
    • Overview
    • Infrastructure Services
    • Management and Operations Services
    • Energy and Sustainability Services
    • Consulting Services
  • Education
    • Course Details
    • Course Calendar
    • Competency & Confidence Assessments
    • Private Education
    • Graduate Roster
  • Events
    • Industry Events
    • Leadership Events
    • Network Events
  • Network
    • Overview
    • Network Calendar
    • Network Roster
    • Request Corporate Access
    • Request Guest Access
    • Uptime Network Portal
  • Intelligence
  • Clients
    • Client Stories
  • Resources
    • Data Center Industry Surveys
    • Ebooks
    • Journal Blog
    • Product Datasheets
    • Research & Reports
    • Tier Specification Documents
    • Tools
    • Webinars
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu
Blog - Latest News
2020

Best-in-class data center provisioning: Simplify, Standardize, Repeat

July 13, 2020/in Design, Executive/by Rhonda Ascierto, Vice President, Research, Uptime Institute

Demand for IT capacity continues to grow rapidly across the globe, which has driven the need for more industrialized approaches to data center provisioning including construction and component assembly. Large operators and their partners have scrambled to apply new processes and disciplines, expand and re-organize supply chains, deploy prefabricated components, and, where possible, reduce cost overheads, variation and complexity.

These approaches have led to dramatically shortened provisioning times in recent years. Globally, the average time to provision a new large data center (20 megawatts or more), following best practices, is just nine to 10 months, according to research by the Uptime Institute Some are provisioned in as little as six months — an incredible achievement given the multiyear timelines of a decade or two ago.

These approaches have also led to lower capital costs (on average). The money required to build a new large data center (20 MW or more), following best practices, has fallen to $7-8 million per megawatt (global average). Some are even able to achieve this for less — as low as $3.6 million per megawatt. This is also significant improvement compared with a decade ago, when $12 million per megawatt was common for data centers typically in the 3-15 MW range. Today, the cost of building a medium-sized data center (5-19.9 MW) can be similar to that of a large data center if best practices are followed.

Factors that affect speed

Achieving the best-case provisioning speed relies on the use of prefabricated systems across all areas and on having access to experienced builders doing repeat builds of standardized construction approaches, supported by a strong local supply chain.

The need to quickly mobilize many construction workers for a brief project at a reasonable price can be a management and logistical challenge — one that requires the availability of considerable local presence and expertise. The workforce will need experience doing repeat builds of standardized construction approaches and, ideally, the specific building system to be installed (e.g., precast concrete, steel).

Most builders have adopted a standard power increment, typically between 1.5 MW and 10 MW, that is repeated in multiples to achieve the total power delivered in a project. Repeating standard configurations, enabling parallel installs and using the same team of experienced workers simplifies material supply, leads to process improvements and reduces provisioning time.

Factors that affect cost

Data center provisioning capital expenses will vary among projects, even when using best practices. This is due to differences in site conditions and location, access to specialist workforces, material and worker transportation, and a range of other variables related to the region (e.g., regulations, seismic activity, supply chains, climate) and facility specifications.

One important aspect that drives cost is power density of the IT racks. Higher density can drive down overall costs. While there could be some trade-offs in electrical equipment and cooling, the main impact of higher density is reduced floor space/building shell, resulting in overall lower building costs.

Custom requirements can also affect both capex and opex. For example, large cloud providers that design their own server hardware can deviate from ASHRAE rules, allowing a wider thermal envelope (usually hotter) and lower opex due to reduced cooling (and thus power) use. This modification may mean lower capex in terms of equipment but may increase some build costs.

The key to building data centers — regardless of size — for the lowest possible cost is similar to the key to building them at the fastest possible speed: repeat proven, standard approaches. Hire the same experienced crews. Consistently use the same engineering, techniques and technologies. Larger projects can reach slightly lower price points by purchasing equipment in larger volumes and by splitting fixed costs over additional megawatts.

There is no single technology or practice that can be credited — these faster, cheaper builds are achieved through a combination of technologies and practices. Data center capacity providers, such as colocation and wholesale leasing companies, that are building large data centers very quickly are competitively positioned to attract large-scale cloud customers — and are likely to continue to refine their processes and approaches to achieve shorter provisioning times, at even lower cost, in the future.

Share this:

  • Share on Facebook (Opens in new window) Facebook
  • Share on X (Opens in new window) X
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Reddit (Opens in new window) Reddit
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Email a link to a friend (Opens in new window) Email
Tags: Data Center, Data Center Design, data center provisioning
https://journal.uptimeinstitute.com/wp-content/uploads/2020/07/Blog-Provisioning.jpg 500 1350 Rhonda Ascierto, Vice President, Research, Uptime Institute https://journal.uptimeinstitute.com/wp-content/uploads/2022/12/uptime-institute-logo-r_240x88_v2023-with-space.png Rhonda Ascierto, Vice President, Research, Uptime Institute2020-07-13 06:00:382020-07-06 13:36:33Best-in-class data center provisioning: Simplify, Standardize, Repeat
You might also like
Liquid cooling will not outgrow its high-density niche Liquid cooling will not outgrow its high-density niche
UI @ 2021 How data center operators can transition to renewable energy
Failure Doesn’t Keep Business Hours: 24×7 Coverage
Vertiv’s DCIM ambitions wither on Trellis’ demise Vertiv’s DCIM ambitions wither on Trellis’ demise
How to avoid outages: Try harder2019 How to avoid outages: Try harder!
24x7 carbon-free energy (part two): getting to 100% 24×7 carbon-free energy (part two): getting to 100%
Understanding how server power management works Understanding how server power management works
Data Center Outages - Part Deux How to Avoid Outages – Part Deux

Content Categories

  • Journal Home
  • Executive
  • Operations
  • Design

Subscribe to Journal via Email

Enter your email address to subscribe to Uptime Institute Journal and receive notifications of new articles by email.

  • Recent

Tags

Accredited Tier Designer (9) AI (21) artificial intelligence (16) ATD (10) Carbon Emissions (7) Climate Change (13) Cloud (22) Cloud Computing (17) Cloud Costs (15) Cloud Infrastructure (29) Cloud Migration (8) Colocation (6) cooling (9) Data Center (252) Data Center Availability (40) Data Center Cooling (13) Data Center Design (45) Data Center Disaster Recovery (7) Data Center Energy Efficiency (34) Data Center Facilities Management (43) Data Center Operations (66) data center power (8) Data Center Staffing (18) DCIM (9) digital Infrastructure (117) energy (8) Energy Efficiency (38) Environmental Sustainability (18) IT (7) IT Efficiency (16) IT Outages (10) M&O (6) outages (11) Public Cloud (7) PUE (10) Regulations (24) Resiliency (9) security (7) Sustainability (34) Sustainability Reporting (7) Tier Certification (26) Tier Certification Constructed Facility (16) Uptime Institute FORCSS (6) Uptime Institute Network (13) Uptime Institute Symposium (6)
© 2014-2025 Uptime Institute, LLC All rights reserved.
  • Link to X
  • Link to LinkedIn
  • Link to Mail
Link to: Cleaning a data center: Contractors vs. DIY Link to: Cleaning a data center: Contractors vs. DIY Cleaning a data center: Contractors vs. DIY Link to: The pandemic, outages and the internet giants Link to: The pandemic, outages and the internet giants The pandemic, outages and the internet giants
Scroll to top Scroll to top Scroll to top