• Link to X
  • Link to LinkedIn
  • Link to Mail
  • ABOUT UI
    • Business Partners
    • Careers
    • Contact Us
    • News & Press
    • Our Team
    • Press Releases
    • Branding Guidelines
  • CONTACT
Uptime Institute Blog
  • Journal
    • Journal Home
    • Executive
    • Operations
    • Design
  • AI Services
    • AI Infrastructure Advisory
    • AI Custom Support
  • Tier Certification
    • Overview
    • Design
    • Construction
    • Operations
    • Tier Gap Analysis
    • Prefabricated/Modular
    • Tier Certifications List
  • Professional Services
    • Overview
    • Infrastructure Services
    • Management and Operations Services
    • Energy and Sustainability Services
    • Consulting Services
  • Education
    • Course Details
    • Course Calendar
    • Competency & Confidence Assessments
    • Private Education
    • Graduate Roster
  • Events
    • Industry Events
    • Leadership Events
    • Network Events
  • Network
    • Overview
    • Network Calendar
    • Network Roster
    • Request Corporate Access
    • Request Guest Access
    • Uptime Network Portal
  • Intelligence
  • Clients
    • Client Stories
  • Resources
    • Data Center Industry Surveys
    • Ebooks
    • Journal Blog
    • Product Datasheets
    • Research & Reports
    • Tier Specification Documents
    • Tools
    • Webinars
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu
Blog - Latest News
Data Center PUE has leveled off since 20132020

Data center PUEs flat since 2013

April 27, 2020/in Executive, Operations/by Andy Lawrence, Executive Director of Research, Uptime Institute, alawrence@uptimeinstitute.com

The average power usage effectiveness (PUE) ratio for a data center in 2020 is 1.58, only marginally better than 7 years ago, according to the latest annual Uptime Institute survey (findings to be published shortly).

PUE, an international standard first developed by The Green Grid and others in 2007, is the most widely accepted way of measuring the energy efficiency of a data center. It measures the ratio of the energy used by the IT equipment to the energy used by the entire data center.

All operators strive to get their PUE ratio down to as near 1.0 as possible. Using the latest technology and practices, most new builds fall between 1.2 and 1.4. But there are still thousands of older data centers that cannot be economically or safely upgraded to become that efficient, especially if high availability is required. In 2019, the PUE value increased slightly (see previous article), with a number of possible explanations.

The new data (shown in the figure below) conforms to a consistent pattern: Big improvements in energy efficiency were made from 2007 to 2013, mostly using inexpensive or easy methods such as simple air containment, after which improvements became more difficult or expensive. The Uptime Institute figures are based on surveys of global data centers ranging in size from 1 megawatt (MW) to over 60 MW, of varying ages.



As ever, the data does not tell a complete story. This data is based on the average PUE per site, regardless of size or age. Newer data centers, usually built by hyperscale or colocation companies, tend to be much more efficient, and larger. A growing amount of work is therefore done in larger, more efficient data centers (Uptime Institute data in 2019 shows data centers above 20 MW to have lower PUEs). Data released by Google shows almost exactly the same curve shape — but at much lower values.

Operators who cannot improve their site PUE can still do a lot to reduce energy and/or decarbonize operations. First, they can improve the utilization of their IT and refresh their servers to ensure IT energy optimization. Second, they can re-use the heat generated by the data center; and third, they can buy renewable energy or invest in renewable energy generation.


More information on this topic is available to members of the Uptime Institute Network here.

Share this:

  • Share on Facebook (Opens in new window) Facebook
  • Share on X (Opens in new window) X
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Reddit (Opens in new window) Reddit
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Email a link to a friend (Opens in new window) Email
Tags: data center power, PUE
https://journal.uptimeinstitute.com/wp-content/uploads/2020/04/GettyImages-1193108294blog.jpg 1000 2700 Andy Lawrence, Executive Director of Research, Uptime Institute, alawrence@uptimeinstitute.com https://journal.uptimeinstitute.com/wp-content/uploads/2022/12/uptime-institute-logo-r_240x88_v2023-with-space.png Andy Lawrence, Executive Director of Research, Uptime Institute, alawrence@uptimeinstitute.com2020-04-27 11:50:272025-10-30 14:46:08Data center PUEs flat since 2013
You might also like
Dual-Corded-Power Dual-Corded Power and Fault Tolerance: Past, Present, and Future
Does the spread of direct liquid cooling make PUE less relevant? Does the spread of direct liquid cooling make PUE less relevant?
Resiliency v low PUE: regulators a catalyst for innovation? Resiliency v low PUE: regulators a catalyst for innovation?
UI 2020 PUE: The golden metric is looking rusty
Data Centers without Generators?2019 Data centers without diesel generators: The groundwork is being laid…
US operators scour Inflation Reduction Act for incentives US operators scour Inflation Reduction Act for incentives
Global PUEs — are they going anywhere? Global PUEs — are they going anywhere?
The Trend of PUE in 2019Uptime Institute Is PUE actually going UP?

Content Categories

  • Journal Home
  • Executive
  • Operations
  • Design

Subscribe to Journal via Email

Enter your email address to subscribe to Uptime Institute Journal and receive notifications of new articles by email.

  • Recent

Tags

Accredited Tier Designer (9) AI (21) artificial intelligence (16) ATD (10) Carbon Emissions (7) Climate Change (13) Cloud (22) Cloud Computing (17) Cloud Costs (15) Cloud Infrastructure (29) Cloud Migration (8) Colocation (6) cooling (9) Data Center (252) Data Center Availability (40) Data Center Cooling (13) Data Center Design (45) Data Center Disaster Recovery (7) Data Center Energy Efficiency (34) Data Center Facilities Management (43) Data Center Operations (66) data center power (8) Data Center Staffing (18) DCIM (9) digital Infrastructure (117) energy (8) Energy Efficiency (38) Environmental Sustainability (18) IT (7) IT Efficiency (16) IT Outages (10) M&O (6) outages (11) Public Cloud (7) PUE (10) Regulations (24) Resiliency (9) security (7) Sustainability (34) Sustainability Reporting (7) Tier Certification (26) Tier Certification Constructed Facility (16) Uptime Institute FORCSS (6) Uptime Institute Network (13) Uptime Institute Symposium (6)
© 2014-2025 Uptime Institute, LLC All rights reserved.
  • Link to X
  • Link to LinkedIn
  • Link to Mail
Link to: COVID-19: Q&A (Part 3): Deferred Maintenance, Remote Work, Supply Chain, Long-Term Outlook Link to: COVID-19: Q&A (Part 3): Deferred Maintenance, Remote Work, Supply Chain, Long-Term Outlook COVID-19: Q&A (Part 3): Deferred Maintenance, Remote Work, Supply Chain,...Uptime Institute's COVID19 Q&A Part 3 Link to: Pandemic is causing some outages and slowdowns Link to: Pandemic is causing some outages and slowdowns Service Outages2020Pandemic is causing some outages and slowdowns